Mahindra & Mahindra Ltd, Zahirabad
This is Dunk type (with EMS) CED line in extension with existing PT line is Designed & Supplied to Mahindra & Mahindra.
Project : CED Plant against AED for 4 wheeler.
Plant Capacity : 240 Vehicles / Day on 2 Shift Basis (15 Jobs/hrs)
Cube size : 2300mmL x 1500mmW x 1500mmH
Weight/Hanger : 300 Kgs.
Scope undertaken : Design, Engineering, Supply, and Erection & Commissioning
- CED Line
- Auxiliary Equipment.
- Electrical Control Panels
- Site electrification
- Plant Automation
- Electrical Control Panels
- SCADA
Project Status : Completed